NASA Logo

NTRS

NTRS - NASA Technical Reports Server

Back to Results
Experiences with Extra-Vehicular Activities in Response to Critical ISS ContingenciesThe maturation of the International Space Station (ISS) design from the proposed Space Station Freedom to today's current implementation resulted in external hardware redundancy vulnerabilities in the final design. Failure to compensate for or respond to these vulnerabilities could put the ISS in a posture where it could no longer function as a habitable space station. In the first years of ISS assembly, these responses were to largely be addressed by the continued resupply and Extra-Vehicular Activity (EVA) capabilities of the Space Shuttle. Even prior to the decision to retire the Space Shuttle, it was realized that ISS needed to have its own capability to be able to rapidly repair or replace external hardware without needing to wait for the next cargo resupply mission. As documented in a previous publication, in 2006 development was started to baseline Extra-Vehicular Activity (EVA, or spacewalk) procedures to replace hardware components whose failure would expose some of the ISS vulnerabilities should a second failure occur. This development work laid the groundwork for the onboard crews and the ground operations and engineering teams to be ready to replace any of this failed hardware. In 2010, this development work was put to the test when one of these pieces of hardware failed. This paper will provide a brief summary of the planning and processes established in the original Contingency EVA development phase. It will then review how those plans and processes were implemented in 2010, highlighting what went well as well as where there were deficiencies between theory and reality. This paper will show that the original approach and analyses, though sound, were not as thorough as they should have been in the realm of planning for next worse failures, for documenting Programmatic approval of key assumptions, and not pursuing sufficient engineering analysis prior to the failure of the hardware. The paper will further highlight the changes made to the Contingency EVA preparation team structure, approach, goals, and the resources allocated to its work after the 2010 events. Finally, the authors will overview the implementation of these updates in addressing failures onboard the ISS in 2012, 2013, and 2014. The successful use of the updated approaches, and the application of the approaches to other spacewalks, will demonstrate the effectiveness of this additional work and make a case for putting significant time and resources into pre-failure planning and analysis for critical hardware items on human-tended spacecraft.
Document ID
20160003091
Acquisition Source
Johnson Space Center
Document Type
Conference Paper
Authors
Van Cise, E. A.
(NASA Johnson Space Center Houston, TX, United States)
Kelly, B. J.
(NASA Johnson Space Center Houston, TX, United States)
Radigan, J. P.
(NASA Johnson Space Center Houston, TX, United States)
Cranmer, C. W.
(NASA Johnson Space Center Houston, TX, United States)
Date Acquired
March 7, 2016
Publication Date
May 16, 2016
Subject Category
Space Transportation And Safety
Report/Patent Number
JSC-CN-35520-1
Meeting Information
Meeting: International Conference on Space Operations (SpaceOps 2016)
Location: Daejeon
Country: Korea, Republic of
Start Date: May 16, 2016
End Date: May 20, 2016
Sponsors: American Inst. of Aeronautics and Astronautics, Korea Aerospace Research Inst.
Distribution Limits
Public
Copyright
Work of the US Gov. Public Use Permitted.
No Preview Available