NASA Logo

NTRS

NTRS - NASA Technical Reports Server

Back to Results
Calibration of the NASA Glenn 8- by 6-Foot Supersonic Wind Tunnel (1996 and 1997 Tests)There were several physical and operational changes made to the NASA Glenn Research Center 8- by 6-Foot Supersonic Wind Tunnel during the period of 1992 through 1996. Following each of these changes, a facility calibration was conducted to provide the required information to support the research test programs. Due to several factors (facility research test schedule, facility downtime and continued facility upgrades), a full test section calibration was not conducted until 1996. This calibration test incorporated all test section configurations and covered the existing operating range of the facility. However, near the end of that test entry, two of the vortex generators mounted on the compressor exit tailcone failed causing minor damage to the honeycomb flow straightener. The vortex generators were removed from the facility and calibration testing was terminated. A follow-up test entry was conducted in 1997 in order to fully calibrate the facility without the effects of the vortex generators and to provide a complete calibration of the newly expanded low speed operating range. During the 1997 tunnel entry, all planned test points required for a complete test section calibration were obtained. This data set included detailed in-plane and axial flow field distributions for use in quantifying the test section flow quality.
Document ID
20120002620
Acquisition Source
Glenn Research Center
Document Type
Contractor Report (CR)
Authors
Arrington, E. Allen
(Sierra Lobo, Inc. Freemont, OH, United States)
Date Acquired
August 25, 2013
Publication Date
January 1, 2012
Subject Category
Research And Support Facilities (Air)
Report/Patent Number
E-18026
NASA/CR-2012-217270
Funding Number(s)
WBS: WBS 122711.03.08.03.01.04
CONTRACT_GRANT: NNC05CA95C
Distribution Limits
Public
Copyright
Public Use Permitted.
No Preview Available