Advanced on-site power plant development technology programA 30-cell stack was tested for 7200 hours. At 6000 hours the stack was successfully refilled with acid with no loss of performance. A second stack containing the advanced Configuration B cell package was fabricated and assembled for testing in 1985. A 200-kW brassboard inverter was successfully evaluated, verifying the design of the two-bridge ASCR circuit design. A fuel processing catalyst train was tested for 2000 hours verifying the catalyst for use in a 200-kW development reformer. The development reformer was fabricated for evaluation in 1985. The initial test plan was prepared for a 200-kW verification test article.
Document ID
19860019939
Acquisition Source
Legacy CDMS
Document Type
Contractor Report (CR)
Authors
Kemp, F. S.
(United Technologies Corp. South Windsor, CT, United States)
Date Acquired
September 5, 2013
Publication Date
February 1, 1985
Subject Category
Energy Production And Conversion
Report/Patent Number
FCR-6848
NAS 1.26:175007
NASA-CR-175007
DOE/NASA/0389-3
Report Number: FCR-6848
Report Number: NAS 1.26:175007
Report Number: NASA-CR-175007
Report Number: DOE/NASA/0389-3
Accession Number
86N29411
Funding Number(s)
CONTRACT_GRANT: DEN3-289
CONTRACT_GRANT: DE-AI21-80ET-17088
Distribution Limits
Public
Copyright
Work of the US Gov. Public Use Permitted.