A Microsoft Project-Based Planning, Tracking, and Management Tool for the National Transonic Facility's Model Changeover ProcessThe removal and installation of sting-mounted wind tunnel models in the National Transonic Facility (NTF) is a multi-task process having a large impact on the annual throughput of the facility. Approximately ten model removal and installation cycles occur annually at the NTF with each cycle requiring slightly over five days to complete. The various tasks of the model changeover process were modeled in Microsoft Project as a template to provide a planning, tracking, and management tool. The template can also be used as a tool to evaluate improvements to this process. This document describes the development of the template and provides step-by-step instructions on its use and as a planning and tracking tool. A secondary role of this document is to provide an overview of the model changeover process and briefly describe the tasks associated with it.
Document ID
19990021249
Acquisition Source
Langley Research Center
Document Type
Contractor Report (CR)
Authors
Vairo, Daniel M.
(Lockheed Martin Engineering and Sciences Co. Hampton, VA United States)
Date Acquired
September 6, 2013
Publication Date
December 1, 1998
Subject Category
Research And Support Facilities (Air)
Report/Patent Number
NAS 1.26:208968
NASA/CR-1998-208968
Report Number: NAS 1.26:208968
Report Number: NASA/CR-1998-208968
Funding Number(s)
PROJECT: RTOP 522-31-51-01
CONTRACT_GRANT: NAS1-96014
Distribution Limits
Public
Copyright
Work of the US Gov. Public Use Permitted.
No Preview Available