Incident Involving 30-Ah Li-ion Cell at NASA Glenn Research CenterThe key lesson learned from the February 17, 2006 cell explosion incident is that PC-based test-systems, even those having built-in watchdog monitors, can lose control and malfunction. In the case of lithiumion cell/battery testing, the stored energy can be released explosively causing considerable injury and damage to facilities. The investigation showed that although the Arbin system has a built-in watchdog monitor, the circumstances of the incident defeated the action of the watchdog and allowed the cycler to continue operation without control. An upgrade to the most recent version of Arbin software (version 4) was provided as a fix to the presumed control problem. This upgrade included newer EPROM s for the cycler microprocessor. Investigation revealed that similar incidents have occurred at other NASA centers with a variety of PC-based test instruments. JPL suffered an incident with Maccor testers and the GRC fuel cell group observed similar problems with LabView software. This is not exclusively an Arbin problem, but an issue with all PC-based systems. In this incident, it was fortunate that the event occurred after-hours with no-one in the room. The facility arrangement placed control consoles adjacent to the test chamber doors. Had someone been in the room during the event, they would have been exposed to hot debris and toxic combustion products. It was also fortunate that the exploded cell stayed inside the chamber after the door was forced open. If the cell had been ejected into the room it could have caused serious facility damage by impact and possibly caused a fire in the facility.
Document ID
20070017328
Acquisition Source
Glenn Research Center
Document Type
Conference Paper
Authors
Bennett, William
(NASA Glenn Research Center Cleveland, OH, United States)
Date Acquired
August 23, 2013
Publication Date
January 1, 2006
Subject Category
Quality Assurance And Reliability
Meeting Information
Meeting: 74th Linthium Battery Technical/Safety Group Meeting
Location: Beaver Creek, OH
Country: United States
Start Date: September 6, 2006
End Date: September 7, 2006
Funding Number(s)
WBS: WBS 038957.04.01.02.03
Distribution Limits
Public
Copyright
Work of the US Gov. Public Use Permitted.