NASA Logo

NTRS

NTRS - NASA Technical Reports Server

Back to Results
Tethered Space Satellite-1 (TSS-1): Technical RoundaboutsIn the early 1990's US and Italian scientists collaborated to study the electrodynamics of dragging a satellite on a tether through the electrically charged portion of Earth's atmosphere called the ionosphere. An electrical current induced in the long wire could be used for power and thrust generation for a satellite. Other tether uses include momentum exchange, artificial gravity, deployment of sensors or antennas, and gravity-gradient stabilization for satellites. Before the Tethered Space Satellite (TSS-1), no long tether had ever been flown, so many questions existed on how it would actually behave. The TSS consisted of a satellite with science experiments attached to a 12.5 mile long, very thin (0.10 inch diameter) copper wire assembly wound around a spool in the deployer reel mechanism. With the Space Shuttle at an altitude of 160 nautical miles above earth, the satellite was to be deployed by raising it from the Shuttle bay on a boom facing away from Earth. Once cleared of the bay, the deployer mechanism was to slowly feed out the 12-plus miles of tether. Scientific data would be collected throughout the operation, after which the satellite would be reeled back in. Pre-flight testing system level tests involved setting up a tether receiver to catch the 12.5 mile tether onto another reel as it was being unwound by the deployer reel mechanism. Testing only the reel mechanism is straightforward. This test becomes more complicated when the TSS is mounted on the flight pallet at Kennedy Space Center (KSC). The system level tests must be passed before the pallet can be installed into the Space Shuttle cargo bay. A few months before flight, the TSS payload had been integrated onto the Spacelab pallet and system level tests, including unreeling and reeling the tether, had been successfully completed. Some of this testing equipment was then shipped back to the contractor Martin Marietta. Systems-level load analyses, which cannot be run until all information about each payload is finalized, was run in parallel with the physical integration of the hardware into the Shuttle payload bay. The coupled loads analysis, as it is called, incorporates any updates to the model due to system level tests, and any changes that were found during integration. The coupled loads analysis revealed that a single bolt attaching the deployer reel mechanism to the support structure had a "negative margin" - which is an indication that it might fail during operation. Hardware certification rules do not allow for hardware to fly with negative margins, so this issue had to be resolved before the flight. Since there is conservatism in engineering analysis, there is an option to "waive" the margin requirement, and fly the experiment as is. On the other hand, a structural failure of one payload could have serious or catastrophic consequences to other payloads and possibly the mission. Minor design changes or fixes might be feasible within the payload bay prior to launch. Any major design changes that required the spooling test to validate the hardware, or for the pallet to be removed, would cause TSS not to be ready for the Shuttle launch.
Document ID
20160005656
Acquisition Source
Marshall Space Flight Center
Document Type
Other
Authors
O'Connor, Brian
(NASA Marshall Space Flight Center Huntsville, AL, United States)
Stevens, Jennifer
(NASA Marshall Space Flight Center Huntsville, AL, United States)
Date Acquired
May 2, 2016
Publication Date
January 27, 2016
Subject Category
Spacecraft Design, Testing And Performance
Report/Patent Number
M16-5266
MSFC-CS1006-1
Report Number: M16-5266
Report Number: MSFC-CS1006-1
Distribution Limits
Public
Copyright
Work of the US Gov. Public Use Permitted.
No Preview Available