NASA Logo

NTRS

NTRS - NASA Technical Reports Server

Back to Results
Launch Complex 34, SWMU CC054 2023 DNAPL Source Zone Operations, Maintenance, and Monitoring, Site-Wide Long-Term Monitoring, and Hot Spot 6 Air Sparge System Annual Performance Monitoring and Phase Two Expansion Construction Completion Report Cape Canaveral Space Force Station, FloridaThis Annual Performance Monitoring Report (PMR) for the Dense Non-Aqueous Phase Liquid (DNAPL) Source Zone (DSZ), Site-Wide Long-Term Monitoring (LTM), and Hot Spot 6 (HS 6) Air Sparge (AS) System presents the results of Year 14 operations and performance monitoring of the hydraulic containment (HC) Interim Measure (IM), details associated with construction and implementation of the HS 6 AS system expansion (Phase Two), and the results of operations and performance sampling of the HS 6 AS IM at Launch Complex 34 (LC34), located at Cape Canaveral Space Force Station (CCSFS), Florida. The timeframe for activities documented in this PMR extends from April 1, 2023 to March 31, 2024. LC34 has been designated Solid Waste Management Unit CC054 under the Kennedy Space Center (KSC) Resource Conservation and Recovery Act Corrective Action Program.

The objective of the HC IM at LC34 is to contain the shallow and deep DSZ and surrounding dissolved-phase trichloroethene (TCE) high concentration plume via operation of a hydraulic containment system (HCS). The pre-IM design 300 micrograms per liter (μg/L) TCE groundwater contour was used to establish the deep zone capture area for deep recovery wells, and the shallow zone capture area was defined by the DSZ. The system began operating in 2010, and in 2015, the system was expanded to provide HC for areas within the 300 μg/L TCE groundwater isocontours of HS 3 and 4. In 2018 and 2019, an investigation was conducted to recharacterize the DSZ, which included investigating TCE mass in Layer 7. This data was subsequently used to optimize the pumping rates of the HCS and install additional recovery wells in Layer 7 to more adequately capture residual contaminant mass.

The operational period for Year 14 of the HCS was from April 1, 2023 to March 31, 2024. Operational runtime for the system was 94 percent during Year 14, with downtime events attributed to planned maintenance, system repairs, and power outages. As of March 31, 2024, a total of 344,849,634 cumulative gallons of groundwater containing 94,656 pounds of chlorinated volatile organic compounds (CVOCs) have been removed by the HCS. During the reporting period covered under this report, the HCS recovered 31,176,393 gallons and approximately 6,319 pounds of CVOC mass. Total combined influent concentrations of TCE have decreased since startup from approximately 280,000 µg/L (January 2010) to 25,000 µg/L (March 2024). During the reporting period, all effluent concentrations from the HCS (aqueous and vapor) were below regulatory reporting limits, indicating the system continues to operate as intended.

Performance monitoring was conducted in January 2024 within the DSZ to evaluate TCE contamination. Groundwater samples were collected via DPT at nine locations, consistent with previous events between 2017 and 2022. Full vertical profile sampling was completed at each DPT from 8 to 98 feet below land surface (bls), at 5-foot intervals. The DPT performance monitoring results are summarized in this PMR. The results revealed TCE remains at concentrations greater than 11,000 µg/L in the DSZ (1-percent solubility, indicative of DNAPL)
at eight of the nine DPT locations and at depths ranging from 28 to 98 feet bls. An overall decreasing trend of TCE concentrations was observed in DPT samples during this reporting period, which is a reduction from the previous event (December 2022) and the peak event in December 2021, where TCE percentages appeared to increase in all depth zones because several recovery wells were turned off during the AS pilot study in the DSZ. The maximum TCE concentration in January 2024 was 1,600,000 µg/L in the 53 feet bls depth interval at DPT594 (previous maximum result in 2022 was 1,800,000 µg/L in the 48 feet bls depth interval at DPT599). This maximum concentration in the 53 feet bls depth interval is in the deep capture zone. During the January 2024 DPT event, the largest portion of TCE mass was observed in the 48 feet bls interval above/within Layer 4. This trend remains consistent with previous years and appears to indicate continued mass discharge from Layer 4 (fine-grained unit).

In addition to DPT sampling, annual groundwater samples were collected from 11 deep monitoring wells in the DSZ area (Layers 7 and 8) in December 2023 to verify vertical and horizontal delineation. Three of the wells were also sampled biweekly to evaluate operations of recovery well RW21D (screened 86 to 106 feet bls), which was installed in January 2023. Of the Layer 7/8 monitoring sampled only annually, results were non-detect or less than groundwater cleanup target levels GCTLs in December 2023, with the exception of one well, IW45D2, which had a cis-1,2-dichloroethene (cDCE), detection greater than the GCTL. Of the three wells sampled biweekly during the operational period, the well located closest to Layer 7 recovery well RW21D (IW44D2, screened 105 to 115 feet bls) had concentrations of TCE, cDCE and vinyl chloride (VC) greater than GCTLs throughout the operational period, but displayed a decreasing trend since the peak concentrations in September 2023. The maximum TCE
concentration during this operational period was 190,000 µg/L at IW44D2 in September 2023, but reduced to 700 µg/L in March 2024, indicating the HCS is still effectively removing mass from the source area. Expansion of the HCS and addition of new recovery wells is ongoing and will continue to be evaluated as the groundwater recovery scheme is optimized. Details of the expansion and optimization will be provided in a future PMR.

The HS 6 AS IM was initiated in 2018 with 160 AS wells and expanded in 2019 with another 140 AS wells. An additional expansion of the HS 6 AS IM was completed during the reporting period covered under this report and details of the construction implementation and startup of the expansion are detailed in Section III of this report. The new expansion, referred to as Phase Two, was implemented between August 17, 2022 and August 28, 2023, and included the installation of 190 air sparge wells to treat an additional 11.2 acres. The original configuration (referred to as Phase One) operated until Phase Two came online, then all but 52 AS wells were turned off so the components could be moved and utilized in the Phase Two area. The 52 AS wells that remain on are in a barrier configuration preventing contaminated groundwater from impacting the treated area. The HS 6 AS system (both Phase One and Two) operated normally during the reporting period covered under this report. Semi-annual performance monitoring of the Phase One configuration was conducted in April and November 2023, consistent with previous years. For the Phase Two configuration, 21 new monitoring wells were installed and sampled quarterly, with a baseline event in July 2023, and quarterly events in November 2023 and February 2024 summarized in this report. Semi-annual monitoring results collected in April and October 2023 show concentrations of contaminants of concern (cDCE, trans-1,2-dichloroethene, and VC) have decreased to less than GCTLs in nearly all wells and not impacting the surface water drainage canal, indicating the HS 6 IM continues to meet objectives. The baseline and quarterly sampling for the Phase Two configuration indicate generally decreasing concentrations in wells within and around the perimeter of the treatment area. At least two more quarters of monitoring will be conducted and once those results are evaluated a reduced the sampling frequency may be considered.

Overall, the tasks associated with Year 14 operation of the HC IM and operation of the HS 6 AS IM were performed in accordance with recommendations included in the previous 2022 LC34 (Year 13) PMR. Evaluation of results from the HC IM and HS 6 IM show that these systems are operating as designed and meeting performance objectives.
Document ID
20240014488
Acquisition Source
Kennedy Space Center
Document Type
Contractor or Grantee Report
Authors
Sarah J Damphouse
(Tetra Tech (United States) Pasadena, California, United States)
Date Acquired
November 14, 2024
Publication Date
July 1, 2024
Subject Category
Engineering (General)
Environment Pollution
Funding Number(s)
CONTRACT_GRANT: 80KSC019F0067
CONTRACT_GRANT: 80KSC019D0011
Distribution Limits
Public
Copyright
Portions of document may include copyright protected material.
Technical Review
NASA Technical Management
Keywords
groundwater remediation
VOCs
hydraulic containment
air sparging
DNAPL
trichloroethene
TCE
No Preview Available