Software Transition Project Retrospectives and the Application of SEL Effort Estimation Model and Boehm's COCOMO to Complex Software Transition ProjectsThe Multimission Image Processing Subsystem (MIPS) at the Jet Propulsion Laboratory (JPL) has managed transitions of application software sets from one operating system and hardware platform to multiple operating systems and hardware platforms. As a part of these transitions, cost estimates were generated from the personal experience of in-house developers and managers to calculate the total effort required for such projects. Productivity measures have been collected for two such transitions, one very large and the other relatively small in terms of source lines of code. These estimates used a cost estimation model similar to the Software Engineering Laboratory (SEL) Effort Estimation Model. Experience in transitioning software within JPL MIPS have uncovered a high incidence of interface complexity. Interfaces, both internal and external to individual software applications, have contributed to software transition project complexity, and thus to scheduling difficulties and larger than anticipated design work on software to be ported.